Special Bridges


Bridges with Length More Than 500 Meters

Bridge across river Godavari on HKR road

Span Arrangement:
(33 x 30) + 22.6 m
Length:
1012.6 m
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across river Gopad on NH-75 E

Span Arrangement:
46 x 20 m
Length:
920 m
Configuration:
PSC beam slab type super structure with Open foundation system

Bridge across river Mahanadi on NH-6

Span Arrangement:
(6 x 46) + 41 + 46
Length:
798 m
Configuration:
Precast segmental 3 span continuous type with Open foundation system

Bridge across river Krishna in Andhra Pradesh

Span Arrangement:
15 x 35 m
Length:
525 m
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across river musi in Telangana on NH-365

Span Arrangement:
20 + (27 x 30) + 20
Length:
850 m
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across river Godavari in Telangana

Span Arrangement:
40 x 40 m
Length:
1600 m
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across river Godavari in Telangana (near Kaleswaram)

Span Arrangement:
36 x 30
Length:
1080 m
Configuration:
PSC beam slab type super structure with pile foundation system

Major Flyovers / Elevated Corridors / Interchange Structures

Interchange structures at LB nagar Junction Hyderabad

Span Arrangement:
6 kms viaduct
Length:
2/3 Lane
Configuration:
PSC beam slab/St steel composite deck type super structure with open foundations

Interchange structures at Uppal Junction Hyderabad

Span Arrangement:
3 kms viaduct
Length:
2/3 Lane
Configuration:
St steel composite deck type with open foundation system

Interchange structures at Kalpana square Junction in Bhubaneshwar

Span Arrangement:
3 kms viaduct
Length:
2/3 Lane
Configuration:
St steel composite deck type with open foundation system

Bridges / ROB's with Spans More Than 45 Meters

Bridge across Backingharm canal near Iskapalli

Span Arrangement:
45 m
Length:
2-Lane
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across Backingharm canal near Pyderu

Span Arrangement:
45 m
Length:
2-Lane
Configuration:
PSC beam slab type super structure with pile foundation system

Bridge across river Karmanasa on NH-2

Span Arrangement:
55 m
Length:
2/3 Lane
Configuration:
PSC box type super structure with pile foundation system

Bridge across river Durgavati on NH-2

Span Arrangement:
52.5 m
Length:
2/3 Lane
Configuration:
PSC box type super structure with pile foundation system

ROB on NH-2

Span Arrangement:
50 m
Length:
2-Lane
Configuration:
Structural steel composite deck with pile foundation system

ROB on road from Tanda - Raebareli road

Span Arrangement:
50 m
Length:
2-Lane
Configuration:
Structural steel composite deck with pile foundation system

ROB on road from Tanda - Raebareli road

Span Arrangement:
60 m
Length:
2-Lane
Configuration:
Structural steel composite deck with pile foundation system

Special Bridges

Bridge across river mulavagu near Vemulavada

Span Arrangement:
38 m
Length:
3-Lane
Configuration:
RC bow string girder type with Pile foundation system

Bridge across river Mahanadi on NH-6

Span Arrangement:
41 + 46 + 41
Length:
2x3 Lane
Configuration:
Precast segmental 3 span continuous type with Open foundation system